New concrete slab with reinforced retaining wall for split levels, new mesh fencing
Fitted durning construction of new concrete ground slab
Delivered June 2023 - in addition to the existing modern fleet- keeping us reliable
Fire retardant temporary fence sheeting
Field access road to working area. Excavated, hardcore base dressed with stone, creating access roadway to new cider facility
Excavation of stanchion bases and floor slab. Arisings stock piled neatly on site, stoned and internal drainage fitted
Concrete floor slab poured after building erected with external apron
Civils works completed handed back to Client, ready for internal fit out and building contractors completion works
Proposed area for car park extension
Excavated, stoned to levels, kerbed, machine laid tarmacadam falling towards existing drainage. Line marked
Plant fleet continually upgraded - latest JCB 3CX, full specification with breaker,front forks
New fleet of Kubota tracked excavators, 1.5 tons through to 8 tons
External yard, mid-winter working,
HGV reinforced concrete base.
New external access ramp constructed with 24hr rapid setting readymixed concrete with armco barrier and handrail
Saw cut, lift out old drainage channel, retain existing ducts. Dowel bar.
Reinforcing mesh to channels. Internal working, maintaining access for other trades.
Excavation begins, drains diverted.
Foundations dug, steelworks tied & placed, pumped concrete placement begins.
Bespoke vertical wall formwork, 15M diameter circle, 2mm tolerance.
Pumped concrete to form vertical walls, formwork stripped.
Planters works completed, handover to client for HGV turntable fitting by specialist.
Saw cut concrete slab lifting, fully electric equipment.
Fully electric equipment reduced level dig, stone infill.
Steel placed & tied, concrete pumped into base.
Bespoke formwork with angle iron.
Pit completion, handover to client ready for specialist equipment fitting by others.